Chapter 17 Corporate Finance 公司理財(cái) 機(jī)械工業(yè)出版社 Ross PPT課件umj
《Chapter 17 Corporate Finance 公司理財(cái) 機(jī)械工業(yè)出版社 Ross PPT課件umj》由會(huì)員分享,可在線閱讀,更多相關(guān)《Chapter 17 Corporate Finance 公司理財(cái) 機(jī)械工業(yè)出版社 Ross PPT課件umj(25頁(yè)珍藏版)》請(qǐng)?jiān)谘b配圖網(wǎng)上搜索。
1、Chapter 17Valuation and Capital Budgeting for the Levered Firm1 1Chapter 17Chapter 17Executive SummaryFinancing and Investment decisions are actually Financing and Investment decisions are actually related.related.A project of an all-equity firm might be rejected,A project of an all-equity firm migh
2、t be rejected,while the same project might be accepted for a while the same project might be accepted for a levered but otherwise identical firm.levered but otherwise identical firm.Previously we assume that the firm is financed Previously we assume that the firm is financed with equity only.The goa
3、l of this chapter is to with equity only.The goal of this chapter is to value a project,or the firm itself,when leverage value a project,or the firm itself,when leverage is employed.is employed.2 2Chapter 17Chapter 17Executive SummaryThree standard approaches to valuation under leverage:APV(adjusted
4、-present-value)APV(adjusted-present-value)FTE(flow-to-equity)FTE(flow-to-equity)WACC(weighted-average-cost-of-capital)WACC(weighted-average-cost-of-capital)3 3Chapter 17Chapter 1717.1 Adjusted-Present-Value ApproachAPV=NPV+NPVFAPV:adjusted present valueAPV:adjusted present valueNPV:value of the proj
5、ect to an unlevered firmNPV:value of the project to an unlevered firmNPVF:net present value of the financing side NPVF:net present value of the financing side effects.effects.4 4Chapter 17Chapter 1717.1 Adjusted-Present-Value ApproachOne can generally think of four side effectsThe Tax Subsidy to Deb
6、tThe Tax Subsidy to DebtThe Costs of Issuing New SecuritiesThe Costs of Issuing New SecuritiesThe costs of Financial DistressThe costs of Financial DistressSubsidies to Debt FinancingSubsidies to Debt FinancingWe consider the tax subsidy only in the following We consider the tax subsidy only in the
7、following example.example.Example One(page 469)Example One(page 469)5 5Chapter 17Chapter 1717.1 Adjusted-Present-Value ApproachConclusion from the example:The value of the project when financed with The value of the project when financed with some leverage is equal to the value of the some leverage
8、is equal to the value of the project when financed with all equity plus the project when financed with all equity plus the tax shield from the debt.tax shield from the debt.6 6Chapter 17Chapter 1717.2 Flow-To-Equity ApproachThe Flow-to-Equity approach is an alternative capital budgeting approach.The
9、 fomula simply calls for discounting the cash flow from the project to the equityholders of the levered firm at the cost of equity capital,rs.s.7 7Chapter 17Chapter 1717.2 Flow-To-Equity ApproachThere are three steps to the FTE approachStep 1:Calculating Levered Cash Flow(LCF)Step 1:Calculating Leve
10、red Cash Flow(LCF)Step 2:Calculating rStep 2:Calculating rs sStep 3:ValuationStep 3:Valuation8 8Chapter 17Chapter 1717.3 Weighted-Average-Cost-of-Capital Method9 9Chapter 17Chapter 1717.4 A Comparison of the APV,FTE,and WACC ApproachesCapital budgeting techniques in the early chapters of this text a
11、pplied to all-equity firms.Capital budgeting for the levered firm could not be handled early in the book because the effects of debt on firm value were deferred until the previous two chapters.1010Chapter 17Chapter 1717.4 A Comparison of the APV,FTE,and WACC ApproachesDebt increases firm value throu
12、gh tax benefits but decreases value through bankruptcy and related costs.APV first values the project on an all-equity basis,and then add the net present value of the debt.1111Chapter 17Chapter 1717.4 A Comparison of the APV,FTE,and WACC ApproachesThe FTE approach discounts the after-tax cash flow f
13、rom a project going to the equityholders of a levered firm(LCF).The discount rate is rs s,which shows that leverage raises the risk to the equityholders.1212Chapter 17Chapter 1717.4 A Comparison of the APV,FTE,and WACC ApproachesAll three approaches perform the same task:valuation in the presence of
14、 debt financing,all three provide the same valuation estimate.The three approaches are markedly different in technique.1313Chapter 17Chapter 1717.4 A Comparison of the APV,FTE,and WACC ApproachesComparison:APV versus WACCAPV versus WACCAPV and WACC display the greatest similarity.APV and WACC displa
15、y the greatest similarity.Both approaches put the unlevered cash flow Both approaches put the unlevered cash flow(UCF)in the numerator.(UCF)in the numerator.However,the APV discounts at rHowever,the APV discounts at r0 0,the WACC,the WACC discounts at rdiscounts at rWACCWACC.Both approaches adjust t
16、he basic NPV formula for Both approaches adjust the basic NPV formula for unlevered firms in order to reflect the tax benefit unlevered firms in order to reflect the tax benefit of leverage.of leverage.1414Chapter 17Chapter 1717.4 A Comparison of the APV,FTE,and WACC ApproachesComparison:Entity Bein
17、g Valued.Entity Being Valued.The FTE approach appears at first glance to be far The FTE approach appears at first glance to be far different from the other two.different from the other two.For the FTE,only the firms contribution to the For the FTE,only the firms contribution to the initial investmen
18、t is subtracted out.initial investment is subtracted out.Under FTE,only the future cash flows to the Under FTE,only the future cash flows to the levered equityholders are valued.levered equityholders are valued.1515Chapter 17Chapter 1717.4 A Comparison of the APV,FTE,and WACC ApproachesA suggested G
19、uidelineNPV of project is exactly the same under each NPV of project is exactly the same under each of the three methods.of the three methods.However,one method usually provides an However,one method usually provides an easier computation than another,and,in easier computation than another,and,in ma
20、ny cases,one or more of the methods are many cases,one or more of the methods are virtually impossible computationally.virtually impossible computationally.1616Chapter 17Chapter 1717.4 A Comparison of the APV,FTE,and WACC ApproachesA Suggested GuidelineUse WACC or FTE if the firms target debt-to-Use
21、 WACC or FTE if the firms target debt-to-value ratio applies to the project over its life.value ratio applies to the project over its life.Use APV if the projects level of debt is known Use APV if the projects level of debt is known over the life of the project.over the life of the project.1717Chapt
22、er 17Chapter 1717.5 Capital Budgeting When The Discount Rate Must Be EstimatedThe previous sections of this chapter introduced APV,FTE,and WACCthe three basic approaches to valuing a levered firm.One important detail remains,we assumed a discount rate.We now want to show how this rate is determined
23、for real-world firms with leverage.1818Chapter 17Chapter 1717.6 APV ExampleIf firms set a target debt-to-equity ratio,we use WACC and FTE for capital budgeting.However,as we mentioned earlier,APV is the preferred approach when there are side benefits and side costs to debt.An example,in addition to
24、the tax subsidy to debt,both flotation costs and interest subsidies come into play.1919Chapter 17Chapter 1717.7 Beta and LeverageChapter 12(page 318)provides the formula for the relationship between the beta of the common stock and leverage of the firm in a world without taxes.Formula 17.3This relat
25、ionship holds under the assumption that the beta of debt is zero.2020Chapter 17Chapter 1717.7 Beta and LeverageThe corporate-tax case.Formula 17.4.It can be seen that leveerage increases the equity beta less rapidly under corporate taxes.This occurs because,under taxes,leverage creates a riskless ta
26、x shield,thereby lowering the risk of the entire firm.2121Chapter 17Chapter 1717.7 Beta and LeverageExample of scale-enhancing project.Example of not scale-enhancing project.2222Chapter 17Chapter 17Summary and Conclusions2323Chapter 17Chapter 172424Chapter 17Chapter 17謝謝觀看/歡迎下載BY FAITH I MEAN A VISION OF GOOD ONE CHERISHES AND THE ENTHUSIASM THAT PUSHES ONE TO SEEK ITS FULFILLMENT REGARDLESS OF OBSTACLES.BY FAITH I BY FAITH
- 溫馨提示:
1: 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
2: 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
3.本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
5. 裝配圖網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 地震中的父與子_課件
- 《大自然你好》
- 新人教版四年級(jí)上冊(cè)億以?xún)?nèi)數(shù)的改寫(xiě)課件
- 第7章 礦井地質(zhì)(精品)
- 人教版六年級(jí)英語(yǔ)上冊(cè)第二單元第一課時(shí)
- 等差與等比數(shù)列的性質(zhì)
- B內(nèi)酰胺類(lèi)抗生素的合理使用
- 英語(yǔ)下冊(cè)《燕子》課件蘇教版
- 同底數(shù)冪的除法課件
- 豐滿(mǎn)二實(shí)驗(yàn)陳麗杰-長(zhǎng)方體和正方體3(教育精
- 《扁鵲見(jiàn)蔡桓公》課件
- (精品)鑒別、鑒定、除雜類(lèi)題目解決方法
- 第七章-擬膽堿藥和抗膽堿課件
- 膀胱腫瘤的護(hù)理查房
- 健康教研活動(dòng)PPT